Concrete work referrals in Orem, Utah(385) 412-2732
Orem Driveways & Concrete
Menu

Concrete RV Pads and Wide Parking Slabs in Orem

Thickness, base, reinforcement and wait times for a concrete RV pad in Orem, plus the city's front-yard parking and driveway-area rules.

This page is for the Orem homeowner whose camper, trailer or boat now sits on gravel, grass or the street. The licensed local contractors that Orem Driveways & Concrete refers homeowners to do the pour. A pad for a heavy vehicle is built differently from a car driveway, and the zoning rules narrow what you can do first.

Can an RV be parked on the grass in the front yard?

Not under the zoning code as it reads today. Orem's zoning code prohibits parking on grass or landscaped areas of a front yard, or of a side yard adjacent to a street, in residential zones. It also says a driveway to an off-street parking space must be paved with asphalt, concrete or pavers (a third-party copy of Orem's zoning code (Zoneomics), chapter 14).

The same chapter caps driveways on a residential lot at 60 percent of the front or side yard they sit in, and caps all driveways on a corner lot at 50 percent of the combined front and street-side yard area. Those caps can decide how wide a pad may be.

Where an RV may be stored on a lot, how large it may be and which side- and rear-yard setbacks apply are the city's calls. Give the City of Orem your address at 801-229-7000 and get the answer before anything is poured.

What is different about a pad built for an RV?

Weight, and where the weight sits. Concrete Network says 4 inches is generally enough for passenger cars and SUVs, and that heavier trucks or a large RV may call for 5 or 6 inches (Concrete Network). The same source says wire mesh generally suits slabs 4 to 5 inches thick and rebar suits those 5 inches or thicker.

Three items belong on an RV-pad quote that a plain driveway quote may skip:

  • Thickness stated for the pad itself, not just the driveway.
  • Reinforcement type. Synthetic fibers cut plastic shrinkage cracking but do not give structural reinforcement like steel, per Concrete Network.
  • Base depth. The compacted subbase and base should be at least 4 inches thick in total, according to Concrete Network. A heavy tongue or jack stand on a thin base is how slabs sink.

How much steel, at what spacing, and how deep the base goes for your vehicle is the contractor's call.

How long before the RV can go on?

Longer than a car. Concrete Network says to wait at least 28 days before driving or parking RVs and large trucks on a new driveway. Cars can typically use it after seven days (source). Driving near the edges early is a common way to crack a new slab.

If the old pad was where the RV spent the winter, plan where it will sit for a month. The contractor can advise on the pour date.

What about the approach at the curb?

If the RV pad connects to the street through a new or widened approach, that part crosses the city's right-of-way. Orem's handout says drive approaches need an Engineering permit (Orem handout, PDF). The city's standard drawing for the combination drive approach calls for concrete 6 inches thick and a 12-foot minimum width (Orem Construction Standard Drawings, PDF).

How wide an approach for a larger vehicle must be is for Orem Engineering to say. Call the city main line at 801-229-7000 and confirm, since rules and fees change. The permits page explains the two offices.

What does it cost?

Nationally, Thumbtack says a concrete driveway costs about $8 to $18 per square foot, and Concrete Network says plain gray costs $5 to $8. A pad built thicker than a normal driveway sits above a thin-slab price, since more concrete and steel go in. The cost page has the ranges; a real quote depends on your lot and the vehicle, so ask for the thickness to be itemized.

Common questions

Should the pad be sealed?

Concrete Network says a driveway should generally be resealed every two years or so, or when the finish shows wear (source). Skip deicers the first winter.

Who checks the underground lines?

Blue Stakes of Utah 811 asks to be notified at least 3 business days before any excavation and says the service is free and required by law (Blue Stakes). Ask the contractor who places the request.

Who decides what a pad needs?

The contractor sizes the pad for the vehicle, and any contractor's license can be checked on the state lookup. To ask for a match, use the form or call (385) 412-2732, or read the contact page.

Where these numbers come from: the national per-square-foot figures are from Thumbtack and Concrete Network, and the apron details are from Orem's handout and standard drawings, all read in November 2026.